Phase I - Irrigation Project

Click to Enlarge
Irrigation Project Timetable:
  • Irrigation System Designed, Reviewed and Approved by Seattle Parks Department --- 8/15/2003
  • North Laurel Hedge Removed, Land Graded and Prepared for New Native Plantings --- 8/1-30/2003
  • Irrigation System Installation Contracts Solicted (8/15), Opened (9/3), Contractor Ready to Begin (9/8)
  • Irrigation in 10/15: Initially North Hedge Area, South Planting Area and East Lawn installed .
  • Plantings in North Edge of Park --- 10/15-11/10/2003