Phase I – Irrigation

Plan

Irrigation Project Timetable

Irrigation System Designed, Reviewed and Approved by Seattle Parks Department — 8/15/2003
North Laurel Hedge Removed, Land Graded and Prepared for New Native Plantings — 8/1-30/2003
Irrigation System Installation Contracts Solicted (8/15), Opened (9/3), Contractor Ready to Begin (9/8)
Irrigation in 10/15: Initially North Hedge Area, South Planting Area and East Lawn installed.
Plantings in North Edge of Park — 10/15-11/10/2003